John Holland Water - Mardi-Mangrove Link Project WP07
 
Involves the installation of 9km of DN1000 sintakote SCL welded and RRJ pipes on the central coast. Includes peripheral scour valve and air valveinstallation. Working in both bush easement and along Yarramalong Road.
 
This scope of works is for the installation of pressure main pipe work for the 19km DN1000 GRP Mardi-Mangrove transfer main:
  • Installation of DN1000 RRJ pipe, with various backfilling criteria
  • Installation of DN1000 GRP Butt and Strapped pipe sections with various backfilling criteria
  • Approximately 1820 meters of the Mardi - Mangrove Transfer Main will be installed in a 'share' trench alongside the Wyong - Mardi Rising Main
  • Connection of the main to the Boomerang Creek Tunnel, including installation of all required pipes and fittings

 
DSCF3778.JPG
Mardi to Mangrove
 
DSCF3779.JPG
Mardi to Mangrove
 
DSCF3780.JPG
Mardi to Mangrove
 
DSCF4030.JPG
Mardi to Mangrove
 

This scope of works is for the installation of pressure main pipe work for the 2.1km DN1000 GRP Wyong-Mardi rising main.

  • Installation of DN1000 RRJ pipe, with various backfilling criteria. Approximately 1900 meters to be installed
  • Installation of DN1000 GRP welded pipe sections with various backfilling criteria. Approximately 150 meters to be installed
  • Approximately 1000 meters of the Wyong-Mardi Rising Main will be installed in a 'share' trench alongside the Mardi-Mangrove transfer main
  • Installation of all pipework to connect the rising main to the Wyong Pumping Station.
Detailed scope of works specific to Wyong-Mardi rising main
  • Approximately 2.1km of DN1000 GRP pipeline (RRJ and installation of the butt and strap joints sections)
     
  • Appoximately 1820 meters of the 2100 meter to be in a shared trench with the Mardi-Mangrove transfer main
  • All road, creek, power (underhead and overhead), communications, oil and gas, servces crossings
  • Installation of all air valves, scour valves, flowmeters, section valves, and associated structures and works
  • Testing of the main.

 
DSCF3770.JPG
Mardi to Mangrove
 
DSCF3775.JPG
Mardi to Mangrove
 
DSCF3776.JPG
Mardi to Mangrove
 
DSCF3782.JPG
Mardi to Mangrove
 
 
DSCF3785.JPG
Mardi to Mangrove
 
DSCF3795.JPG
Mardi to Mangrove
 
DSCF3796.JPG
Mardi to Mangrove
 
DSCF3957.JPG
Mardi to Mangrove
 
 
DSCF3836.JPG
Mardi to Mangrove
 
DSCF3851.JPG
Mardi to Mangrove
 
DSCF4013.JPG
Mardi to Mangrove
 
DSCF4022.JPG
Mardi to Mangrove
 
 
DSCF3962.JPG
Mardi to Mangrove
 
DSCF3964.JPG
Mardi to Mangrove
 
DSCF4033.JPG
Mardi to Mangrove
 
DSCF4040.JPG
Mardi to Mangrove
 
 
DSCF4028.JPG
Mardi to Mangrove
 
 
 
 
Home  |   Water Projects   |   Sewer Projects   |   Electrical Projects   |   Gallery   |   Social Responsibility   |   Stakeholder Feedback
  Certifications & Policies   |   Current Insurances   |   Mardi to Mangrove   |   Nuwarra Road, Moorebank   |   Killard Excavation - Freemans Reach   |   Killard Excavation -Breakfast Creek
  Killard Excvation - M2C Canberra   |   Reeds - Northwest Precinct   |   Contact
self-updatable website design by havealook