The Reed Group - Northwest Precinct Works: Watermain work lot 12 - Kellyville, Sydney
 
Involved the installation of 4.5km of DN450, 750, 900 and 1050 DICL and Sintakote SCL pipe, including thrust bores, concrete encasement and major thrust block design. Includes dual and triple main installation within shared trench within trench within roadway. Welding works, inspection points, valves, hydrants, and connections.
 
Watermain laying was to Sydney Water standards and supervised by Australian Water.
 
Last updated: 6/2/2012

 
DSCF3151.JPG

Restoration post dual main installation

 
DSCF3221.JPG
Reed Construction - Work lot 12

 
DSCF3341.JPG
Laying cement in a ditch for Reed Construction -Work lot 12

 
DSCF3130.JPG
Corridor was constructed
 

January 2010 - January 2011
 
 
This project involved the installation of 3km of DN300, 375, and 450 polypropylene pipe SN10, 000 in Kellyville, Sydney. The project was commissioned in order to supply a new trunk sewermain to the growing population in the Northwest Sydney area.
 
Works included site establishment, compound setup, management of deliveries, installation of pipework through sensitive bushland easement, thrust bores across roads, and reinstatement of works. Concrete manholes were constructed at both 1200 and 1800mm diameter, two coats of epoxy seal was applied as per EPM 2, and induct / educt ventshafts were erected along the line. Connections to existing sewer infrastructure established via the implemtation of a flow management plan.
 
Sewer main laying to Sydney Water standards and supervised by Australian water.
 
Last updated: 6/2/2012

 
DSCF3017.JPG
Access to bore pits
 
SDC13121.JPG
Work occured in bush easement and strict environmental controls were observed
 
DSCF3060.JPG
Thrust bores
 
DSCF3081.JPG
Construction of sewer structures
 

June 2010 - January 2011
 
 
Installation of 6.3km of DN450, 750 and 900 DICL and Sintakote SCL pipe including 7 thrust bores, concrete encasement and major thrust block design. Included dual and triple main installation within shared trench within roadway. Welding works, inspection points, valves, hydrants, and connections.
 
This project also included 800m of section through backyards. These areas required PCR's to be obtained, fences removed and temporary fences installed. On completion of works the area was reinstated, and the temporary fences were removed and permanent fencing was re-erected.
 
A corridor was constructed through backyards be erecting ATF fencing once back trees were taken down. Strict access controls were adhered to and PCCA's obtained and signed off.
 
Bores included a 60m bore under Sunnyholt Road (RTA) and a bore under a Caltex Garage entrance.
 
Watermain laying to Sydney Water standards and supervised by Australian Water.  All trench walls were geotechnically tested daily for stability where shoring could not practically be used.
 
Last updated: 6/2/2012

 
IMG00266-20100917-111.jpg
Dual lift of DN900 sintakote pipe
 
IMG00036-20100803-121.jpg
Reed Construction - Work lot 11
 
IMG00274-20100917-112.jpg
Welding setup
 
IMG00041-20100803-121.jpg
Reed Construction - Work lot 11

 
 
Image0043.jpg
Access corridor
 
Image0051.jpg
Access corridor
 
 
 

2010
 
The Reed Group - Worcester Road, Rouse Hill
 
A 1050mm diameter RCP overflow line running from the Rouse Hill Reservoir down Worcester Road in Rouse Hill was newly constructed in the roadway. Works included traffic control, sawcutting pavement, installed 700m of reinforced concrete pipes, precast 1500mm x 1500mm concrete pits, insitu headwall and dissipater structure.
 

 

Last updated: 6/2/2012

 
January 2010 - November 2010
 
 
Involved the installation of 700m DN1050 RCP's including precast pits, headwall, dissipator, and security fencing.
 
The scope of works included:
  • Site establishment
  • Installation of precast pits, pit risers, converter slabs, and access covers
  • Supply and place concrete blinding and benching
  • Supply and installation of valves spindle, shroud pipe, shroud pipe support, and surface box
  • Supply and installation of hydrophillic seals at pipe penetration
  • Supply and install infill at pipe penetrations to ensure water-tightness
  • Supply and installation of structures, including fencing
  • Supply, installation, and maintenance of environmental controls
Sewer main laying to Sydney Water standards and supervised by Australian Water.
 
Last updated: 6/2/2012

 
SDC13035.JPG
Reed Construction - Work lot 7

 
SDC13041.JPG
Reed Construction - Work lot 7

 
SDC13045.JPG
Reed Construction - Work lot 7

 
SDC13015.JPG
Reed Construction - Work lot 7

 

December 2009 - March 2010

 

 
This project involved the installation of 1km of DN300, 375, and 450 polypropylene pipe SN10, 000 in Kellyville, Sydney. The project was commissioned in order to supply a new trunk sewermain to the growing population in the Northwest Sydney area.
 
Works included site establishment, compound setup, management of deliveries, installation of pipework through sensitive bushland easement, thrust bores across roads, and reinstatement of works. Concrete manholes were constructed at both 1200 and 1800mm diameter, two coats of epoxy seal was applied as per EPM 2, and induct / educt ventshafts were erected along the line. Connections to existing sewer infrastructure established via the implementation of a flow management plan.
 
Sewer main laying to Sydney Water standards and supervised by Australian Water.
 
Last updated: 6/2/2012

 
DSCF2460.JPG
A machine assisting pipelaying for Reed Construction - Northwest Precinct
 
SDC13086.JPG
Reed Construction - Northwest Precinct

 
untitled.JPG
Works occured in bush easement and strict environmental controls were observed
 
SDC13184.JPG
Finished product for Reed Construction - Northwest Precinct

 
Home  |   Killard Exacavation - About Us   |   Killard Excavation - Water Projects   |   Killard Excavation - Sewer Projects   |   Killard - Electrical Projects   |   Killard Excavation - Gallery   |   Killard - Social Responsibility
  Killard - Stakeholder Feedback   |   Killard - Certifications & Policies   |   Killard - Current Insurances   |   Killard Excavation - Mardi Mangrove   |   Killard Excavation - Nuwarra Road   |   Killard Excavation - Freemans Reach
  Killard Excavation - Queensland   |   Killard Excavation - M2C Canberra   |   Killard Excavation - NWGC   |   Contact
self-updatable website design by havealook